The Planning Fallacy
Thinking, Fast and SlowThis flow follows the rise, exposure, and partial correction of unrealistic plans based on private circumstances rather than comparable cases.
increasing
Bearing strength in each event
decreasing
Curriculum Optimism

A Two-Year Forecast
Inside View
The curriculum team predicts completion from its own progress and enthusiasm.
Missing History
No one initially asks how similar projects actually ended.
Reference-Class Shock

Seven Years or Failure
Outside Information
Seymour Fox recalls that many comparable teams failed and successful ones took seven to ten years.
Unwelcome Baseline
The statistics contradict the team's confident schedule.
Irrational Perseverance

Refusing to Quit
Sunk Commitment
The team continues despite recognizing that its original plan was unrealistic.
Emotional Cost
Embarrassment and inertia replace explicit decision analysis.
Project Completion

A Delayed Book
Unforeseen Obstacles
Illness, divorce, bureaucracy, and coordination problems consume years.
Failed Mission
The curriculum is completed but never used by the ministry.
Reference-Class Remedy

Forecasting from Distribution
Baseline First
Planners identify a relevant class and use its actual outcomes.
Case Adjustment
Specific evidence modifies the baseline only when it is genuinely diagnostic.
During the author's work with the Israeli Ministry of Education
The Friday afternoon planning meeting
Immediately after the reference-class revelation
Eight years after the team began
Near the end of Part 3