Truman rebuilds the White House
TrumanTruman rebuilds the White House as both a major structural reconstruction and an effort to preserve the presidency’s most visible home. Faced with a building on the verge of collapse, Harry S. Truman chose to retain its exterior walls while replacing nearly everything inside. The work transformed the mansion for the atomic age, but also gave Truman a deeply personal role in restoring what he regarded as a shrine of American democracy.
The building and the decision
By 1949, the White House’s last major overhaul—undertaken in 1902 under Theodore Roosevelt—had left serious structural problems unresolved. That earlier renovation had given the main floor Beaux-Arts elegance, but it was chiefly cosmetic and carried out in haste. In the decades that followed, structural loads strained interior bearing walls; beams had been cut or notched to accommodate plumbing and wiring; and much of the second floor, rebuilt after British soldiers burned the house in 1814, was unsafe. Plumbing, heating, and electrical systems were also outdated or inadequate. Although the sandstone exterior, roof, and fire-resistant third floor added in the 1920s remained stable, the rest of the building faced possible collapse and posed a fire hazard.
The central choice was whether to strip and rebuild the interior below the third floor while retaining the outside walls, or dismantle the whole building and preserve its exterior stones for reassembly. Taking down the walls would have made the project easier and could have saved $300,000 or $400,000. But to Truman, pulling down the White House was unacceptable; he never considered that option. The exterior would remain while the interior was renewed, a practical decision inseparable from the building’s emotional and political meaning.
Truman wanted full responsibility for the work, arguing that it was the President’s house, but Congress declined to give him sole control. A six-member Congressional Commission on the Renovation of the Executive Mansion was established, including representatives of both houses of Congress and leaders from engineering and architecture. Kenneth McKellar, then president pro tempore of the Senate, chaired it, and retired Major General Glen E. Edgerton became executive director. White House architect Lorenzo Winslow worked most directly with Truman. The commission organized the project, but Truman made nearly all its major decisions and many smaller ones. In the spring of 1949, Winslow recorded Truman’s desire for a thorough restoration whose structure and principal fixed finishes would endure for generations.
Reconstruction from the inside out
Dismantling began on December 13, 1949, after six months of planning. Workers first removed the interior piece by piece, then demolished it on a larger scale until the White House was a hollow shell: its outside walls held in place by steel framing. Excavation made room for two new basement levels. Truman relished inspection tours, sometimes walking high above the ground on workers’ catwalks. In his diary he described the new steel and concrete as more substantial than what he had seen in the Empire State Building or the Pentagon.
The reconstruction also enlarged and modernized the house. Before the work, the mansion had 62 rooms, 26 halls and corridors, and 14 bathrooms. The completed building would have more than 100 rooms, 40 halls and corridors, and 19 bathrooms, along with 147 windows, 412 doors, 29 fireplaces, 12 chimneys, and three elevators. Many additions occupied the third floor and the new basements, where a laundry, medical and dental clinics, staff kitchen, barbershop, storage, and service spaces formed an institutional, hotel-like complex. The building received advanced electrical, plumbing, heating, and air-conditioning systems, as well as a television broadcast room. Mechanical equipment alone cost more than $1,250,000; the air-conditioning compressors required additional excavation beside the North Portico.
The reconstruction was not an unqualified act of preservation. As demolition accelerated, large quantities of old pine flooring, doors, plumbing fixtures, brick, and stone were sent to Forts Belvoir and Myer in Virginia, much of it destined for landfill. Chair rails, door frames, and plaster moldings were also discarded, even after moldings had been measured and cast for reproduction. The losses reflected the pressure to finish the work in a reasonable time and at an acceptable cost, but later preservation standards would regard much of the discarded material as a needless sacrifice. The project saved the mansion’s outer form while allowing much of its historic interior fabric to disappear.
A shelter built for the nuclear age
The new basements also answered the fears of the Korean War’s first months, when another world war seemed possible. On the advice of the United States Secret Service and Truman’s military advisers, an additional $868,000 was spent to make the lowest basement bombproof. The protective work required many tons of steel and concrete and was hurried forward; the shelter was completed in less than a year, well before the upper floors were ready.
Its entrance lay at the end of a subterranean passage and was secured by a four-inch steel door. Plans assumed that people arriving after an atomic attack might need to remove radioactive contamination: occupants would shed their clothes in an entrance hall, shower in the next room, and put on emergency clothing. Beyond were army cots, gas masks, chemical toilets, and acetylene torches in case occupants had to cut through the door. Other rooms held a generator, Army rations, and communications equipment, including direct telephone lines to the Pentagon, state police headquarters, and a secret military relocation center near Leesburg known as Mt. Weather. The President and his family were allotted an 8-by-10-foot room with four bunk beds, a toilet, and books. This concealed emergency infrastructure made the renovated residence a domestic home and a potential wartime refuge at once.
Restoration, reopening, and public meaning
The planned budget was $5,412,000, but the final cost reached $5,832,000. Truman believed that the work could have been completed for less and more quickly had he been fully in charge, yet he was pleased with the result. After touring the East Room, Green Room, Blue Room, Red Room, and State Dining Room with Bess Wallace Truman, he recorded that the rooms and state stairway were lovely and that, despite the trouble and worry, the work had been worth it. Architects and engineers told him the building should last another five hundred years; he hoped it would last a thousand.
The renovation mattered to Truman beyond its engineering. He understood the White House as a symbol of the office, and found relief from the burdens of war, scandal, and politics in the work of saving and returning it to service. His earlier use of the presidential yacht, plane, railcar, and limousines had likewise reflected his sense that the forms surrounding the presidency represented its dignity. The mansion’s restoration let him act once more as a builder, this time as guardian of what the narrative calls one of American democracy’s shrines.
When the house reopened for public tours on April 22, 5,444 people visited. On May 3, Truman led a televised tour carried by all three networks, watched by 30 million people. With no script, he moved through the rooms in a relaxed and knowledgeable manner, demonstrating the Steinway piano in the East Room with part of Mozart’s Ninth Sonata, then playing a few bars on an American-made Baldwin piano. The renovation thus ended not only with a rebuilt residence, but with Truman presenting it directly to a national audience: a private home remade as public symbol, its renewed rooms made visible through the same presidential authority that had guided their reconstruction.